Decision Maker: Director of Growth and Assets
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Approval is granted to award Bloom Demolition
& Excavation Ltd. the contract for the Demolition of Various
Council Properties at the rates set out in tender ref:
NEDDC/00000207/2020
Bloom Demolition & Excavation Ltd. are recommended to be
awarded the contract as the most economically advantageous tender
as required by PART 4 SECTION 10.1.
As per Cabinet minute number 78 of 27th June
2018, seven properties at Pine View, Clay Cross were approved for
demolition as part of the refurbishment of the site. Cabinet Minute
724 of 9th May 2018 approves the demolition of 14-16 High Street
Apperknowle and 10-12 Nether Avenue, Killamarsh. The
Council’s AMG agreed, on the 29th October 2019, to the
demolition of seven garages at Malthouse Lane, Ashover. All
properties were deemed to be beyond economical repair.
In accordance with the Council’s Constitution PART 4 -
CONTRACT RULES SECTION 5.5; The contract was advertised as an open
tender via the council’s Procurement section. There were five
returns.
Award the contract to one of the other
companies who submitted a higher priced RFQ. This would result in
North East Derbyshire District Council paying more for the
Demolition of Various Council Properties and not meeting best
value.
Not enter into a contract for the service. This would mean that the
demolitions could not be carried out, the redevelopment of Pine
View would remain incomplete and the properties would be a further
liability to North East Derbyshire District Council.
Publication date: 23/11/2022
Date of decision: 06/07/2020