To increase membership fees as set out at
Appendix A (exclusive of VAT), across all our Leisure Facilities,
from 1st April 2025
In order to offset the uplift in expenditure
to the service, we propose to increase all our current memberships
by £3.00 a month. This will include all direct debit
memberships, annual memberships, and concessionary memberships.
Please refer to Appendix A for the new charges.
Direct debit memberships will continue to be offered as
non-committed contracts (or monthly rolling contracts), and a
joining fee will not be charged to ensure the memberships remain
affordable to residents.
Direct debit memberships have not been increased for over 12 years
to support our communities through difficult periods, such as the
cost of living crisis, the COVID-19 pandemic, and to provide
affordable access to our Leisure Centres. However, the increased
cost of staff resources, services, licences, goods, etc.,
necessitates this increase to ensure the financial stability of the
service.
It is forecast that this increase will generate approximately
£228,000 a year (breakdown provided in Appendix B) and will
be introduced from 1st April 2025.
A competitor analysis has been conducted to ensure we remain
competitive against our local competition, particularly Local
Authority facilities that provide a swimming pool. The APSE
‘State of the Market’ report identifies an industry
average (at the end of 2023) of £33.77 for a typical full
membership fee. This demonstrates that our fee of £33.00
remains competitive and offers value for money to our all our
residents.
1. A "do nothing" approach is not sustainable
for the delivery of chargeable services, particularly where the
services are wholly dependent on income generation. Membership fees
need to be increased to offset the rise in operational costs.
2. Keep all membership charges as they currently are for 2025 or
reduce the monthly fee. Rejected - the proposed £3.00
increase strikes a balance between the financial viability of the
facility and value for money for residents.
Publication date: 04/08/2025
Date of decision: 04/02/2025
Accompanying Documents: