Decision Maker: Assistant Director of Property Estates and Assets
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To agree to the appointment of Bloom
Demolition & Excavation to carry out demolition works at North
Wingfield and Mickley
The demolition of 20 properties, all of which
have been deemed either structurally unsound or beyond economical
repair, is required to facilitate redevelopment and stock
management by Rykneld Homes. 16 of the properties are in North
Wingfield and are being demolished as part of planning 22/00057/FL,
which will provide 70 new properties. The remaining four are in
Mickley and have been condemned so are being demolished as they are
not structurally sound. The plot vacated by one pair will be
surfaced to provide additional parking and the other will be
considered for sale or redevelopment at a future date.
A full tender was carried out for the works and six responses were
received with costs ranging from £89,000 to £262,000.
Following the evaluation of the tender, Bloom D&E were shown to
be best value and satisfy all quality and due diligence
criteria.
Not carry out the works. This was rejected as
the works are required to facilitate a large scale development on
one site and improved parking at another. Failure to carry out the
works would mean the development work could not go ahead and
structurally unsound properties would remain in the Council’s
housing portfolio.
Publication date: 30/11/2022
Date of decision: 20/11/2022
Accompanying Documents: